Step One:
Contact SCE’s Customer Service Center at 1-800-655-4555 to request service. Select option 3 and follow the prompts. The Customer Service Representative will then assign your request to the appropriate local SCE Service Center. The service center will then assign your request to a local service planner who will contact you within 5 business days. Please note that emergency work may affect this timeline.
Step Two:
Your assigned planner will contact you to discuss the details of your project (or, if applicable, provide results of a meter spot review) and request completion of additional forms and information which may include:
- Submittal of a fully completed Customer Project Information Sheet
- Design Option Letter – This Letter of Authorization is required for any projects requiring a drawing. If SCE design is selected, then SCE Local Planning will do the design. If Applicant design is selected, the project will be directed to Tract Planning to review the design that was created by an SCE approved drafter. Speak with your assigned local planner for more information.
- Site Plan(s) - CAD File (2018 version or earlier)
- Temporary Power application
- Outage request form
- Panel single line
- Load calculations
- Grant deed
- Additional information as is applicable to your project
Step Three:
Your assigned planner will continue to work with you to review and explain the timeline and scope of your project.
Remember to start early! This is a two-way conversation between the customer and assigned planner. It’s important to have regular communication together to keep your project on track. Depending on the customer's construction timeline and the submittal/completion of all requirements, the energizing process varies in length of time (also contingent upon customer redesign requests & emergency work). The earlier you contact SCE to start your project the better. Again, SCE is committed to servicing our customer’s needs in providing safe and reliable energy in a timely manner. Contact us today and get started.
See the chart below showing the general scope and deliverables for completing a project through SCE’s Local Planning department: